The hanging overhead crane usually is suspension bridge crane, because of its light duty. The hanging overhead crane max. capacity is 10 ton, always used in warehouse and workshop to load and transport workpieces, steel, etc for components assembly, manufacturing processing, pallet shipment, storage and loading unloading, equipment maintenance.
When delivery, the hanging overhead crane will be divide into some piece for easy transportation, main beam, end beam, motor, wheels, electric hoist and electric accessory. Before installtation, please read the user manual carefully, and notice the following notes:
1. Main beam and end beam installation
Referring to assembly drawing (deliver with goods together), when the suspended overhead crane install onto the track, should ensure there is clearance 3~5mm at each side between wheel and I-beam, you can adjust the clearance by gasket.
2. Electric hoist installation
The electric hoist must be install onto the main beam beforehand and spanned on the track together with crane beam.
3. Electric device installation
We will send detail electric device assembly drawing, please must install all as the drawing.
4. After all electric control circuitry switch on, please adjust two traveling motors to make them rotation in the same direction. And, must make sure the crane action direction is consistent with controller push-button.
5. All traveling motors are conical rotor motors, when turning on the motor, motor shaft will do axial movement, ranging between 0.5mm - 2mm. With brake ring worn, the slippage will be larger, when it reaches to 3 - 4mm, should adjust it back to 0.5mm - 2mm. After three tims adjustment, should be replace brake ring.
- Single Girder Overhead Cranes Delivery To F
- LH double girder bridge crane for sale
- Overhead bridge crane maintenance points
- Grab bucket overhead crane design
- Overhead bridge crane grab classification
- Explosion proof single girder overhead cran
- Overhead crane lifting rule
- What are the overhead travelling crane brak
- Material lifting equipment inspection cycle
- Overhead bridge crane speed control